The Homes Lab
Sign In Register
Design & Estimate Designs Community Contact
How Much Cement, Sand & Ballast You Need Per Cubic Metre of Concrete
Article
How Much Cement, Sand & Ballast You Need Per Cubic Metre of Concrete
Ordering concrete materials shouldn't be guesswork. This guide gives you the exact cement, sand, and ballast needed per cubic metre of concrete for every common mix — from 1:2:4 to 1:1:2 — in bags, cubic metres, and tonnes. You'll also learn the simple formula behind the numbers so you can scale it to any slab, foundation, or column on your site.
The Homes Lab
The Homes Lab Verified
@thehomeslab
Aug 23, 2026 36 views 0 discussions 2 favourites

Walk onto any building site and you'll hear the same anxious question: "How many bags do we order?" Guess too low and work stops while someone runs to the supplier; guess too high and your money sits in a pile getting rained on. The truth is, the quantities are completely predictable — concrete is just cement, sand, and ballast in fixed proportions. Here's exactly how much of each you need per cubic metre, for every common mix, plus the simple formula to scale it to any job.

The quick reference: per 1 m³ of concrete

Mix (cement : sand : ballast)Typical useCement (50 kg bags)SandBallast
1 : 4 : 8Mass concrete / blinding~3.40.47 m³ (~0.8 t)0.95 m³ (~1.4 t)
1 : 3 : 6Class 10 — mass concrete~4.50.46 m³ (~0.7 t)0.92 m³ (~1.4 t)
1 : 2 : 4Class 20 — foundations & slabs~6.50.44 m³ (~0.7 t)0.88 m³ (~1.3 t)
1 : 2 : 3Class ~25~7.50.51 m³ (~0.8 t)0.77 m³ (~1.2 t)
1 : 1.5 : 3Class 25 — columns & beams~80.42 m³ (~0.7 t)0.84 m³ (~1.3 t)
1 : 1 : 2Class 30 — high-strength~110.39 m³ (~0.6 t)0.77 m³ (~1.2 t)

Figures are per cubic metre of finished concrete, using 50 kg cement bags and standard material densities. They're rounded for ordering.

How the calculation works

Those numbers come from one simple, standard process. For any amount of concrete:

  1. Start with the wet volume — the finished concrete you need (say 1 m³).
  2. Convert to dry volume. Loose, dry materials take up more space than the compacted concrete they become, so you multiply by 1.54. One cubic metre of concrete needs about 1.54 m³ of dry materials.
  3. Split by the mix ratio. Add up the parts — for 1:2:4 that's 1 + 2 + 4 = 7 — then give each material its share of the 1.54 m³: cement gets 1/7, sand 2/7, ballast 4/7.
  4. Convert to buying units:
    • Cement — one 50 kg bag is about 0.0347 m³, so divide the cement volume by 0.0347 to get bags.
    • Sand — about 1.6 tonnes per m³.
    • Ballast — about 1.5 tonnes per m³.

That's the entire method. Everything else is just multiplication.

A worked example

Say you're casting a concrete slab measuring 5 m Ã- 4 m Ã- 0.15 m. That's 3 m³ of concrete. Using a standard 1:2:4 mix, just multiply the per-cubic-metre figures by 3:

  • Cement: 6.5 Ã- 3 = ~20 bags
  • Sand: 0.44 m³ Ã- 3 = 1.32 m³ ≈ 2.1 tonnes
  • Ballast: 0.88 m³ Ã- 3 = 2.64 m³ ≈ 4 tonnes

Three numbers, no surprises at the gate.

From cubic metres to tonnes to lorries

Suppliers usually sell sand and ballast by the tonne, and deliver by the lorry, so it helps to think in those units. Using the densities above, sand runs about 1.6 tonnes per cubic metre and ballast about 1.5 tonnes per cubic metre. A typical 7-tonne tipper, then, carries roughly four to five cubic metres — so a small slab like the one above sits comfortably within a single load, while a big foundation pour will need several.

A few things that change the numbers

  • Always add a little extra. Build in 5–10% for wastage — spillage, over-excavation, and what sticks to the mixer.
  • Nominal mixes have limits. The ratios above are fine for general work, but structural elements (suspended slabs, columns, beams carrying load) should follow an engineer's design mix, not a rule of thumb.
  • Bag size matters. These figures assume 50 kg bags; adjust if your cement comes in a different size.
  • Wet sand lies. Very damp sand "bulks up" and can throw your volume off, so buy from a consistent source and measure carefully.

Skip the math entirely

You don't have to do any of this by hand. Our Foundation Concrete Calculator runs the whole formula for you — enter your perimeter, width, depth, and mix, and it returns the exact bags of cement, tonnes of sand and ballast, lorry loads, and cost, with the working shown. Plug in your numbers and order with confidence.

The bottom line

Concrete quantities aren't a mystery — they're arithmetic. Know your volume, multiply by 1.54, split by your mix ratio, and convert to bags and tonnes, and you'll order exactly what you need: no costly stoppages, no wasted materials baking in the sun. Keep this table handy, add a little for wastage, and let the calculator handle the rest.

This is general guidance using standard quantity-surveying figures. Nominal mixes are indicative; for load-bearing structural concrete, always follow a qualified engineer's design mix.
36 views
Discussions 0

No discussions yet

Be the first to share your thoughts on this article.

Summarize with AI
Get a quick AI rundown of this post — opens your preferred assistant with the article ready to summarize.
Engagement
36 Views
2 Favourites
0 Discussions
View Discussions
Written by
The Homes Lab
The Homes Lab
Verified Seller
@thehomeslab
Member since Apr 2026
Sign in to interact
Sign in or create an account to favourite, save and comment.
Delete Comment
Are you sure you want to delete this? Its replies and images will also be removed. This cannot be undone.
0%
Uploading…
Please don’t close this page